What is LOD and which one do I need to procure?

LOD measures how much of the element is defined and reliable in the model — from 100 (concept) to 500 (as-built). The right question is never “what is the LOD?”: it is “what is the LOD for this use?”.

In one sentence: LOD (Level of Development) is a scale from 100 to 500 that says how much the information of each element in the model can be trusted — formalised in the BIMForum LOD Specification (inherited from the American AIA) and nowadays coexisting with the LOIN of the European standard, covered below.

ladder100 → 500 concept → as-built
the band this collective delivers200 – 350 design basis to coordination
the European standard calls itLOIN EN 17412-1 · ISO 19650
mentions in Portuguese competitions (2010–2026)0 / 1,059 measured

1 · The ladder, step by step

Each step buys a new use. The underlined band is where almost all real projects live — and it is the band up to which this collective delivers: LOD 350 at most, no 400/500.

100200300350400/500 concept ·symbol approximateelement defined:measurable coordination+ interfaces fabrication ·as-built THE BAND WORTH PAYING FOR IN MOST CASES
The LOD ladder. The reliability of the information goes up with the step — and so does the modelling cost, whether you use it or not.
stepwhat is definedthe use it buys
LOD 100The element exists as a symbol or conceptual mass; quantities are order of magnitude.Feasibility studies, massing, programme.
LOD 200Approximate element: generic quantity, size, shape, position and orientation.Preliminary design basis, estimates, application.
LOD 300Defined element: specific size, shape, location and identity. It can be measured from the model.Permitting design, quantity take-offs, budget.
LOD 350LOD 300 + interfaces with the neighbouring systems (supports, connections, clearances).Discipline coordination, clash detection.
LOD 400Fabrication, assembly and installation detail.Construction: model-guided execution.
LOD 500Element verified against the built work (as-built).Asset management, maintenance.
Detail is not development. An element can look like a render and still be no more than LOD 200 in verified information — and the other way round. LOD always refers to reliability of information, not graphic richness. That is why you procure by use and not by beauty.

2 · What the standard calls this: LOIN

ISO 19650 does not use LOD. It uses LOIN (Level of Information Need, formalised in EN 17412-1): instead of a single scale, one defines per element and per purpose — required geometry, alphanumeric data, documentation — which information that use needs (sizing, coordinating, awarding, managing). At the drawing board: “LOD 300” is the conversational shortcut; LOIN is the answer a tender document under the ISO 19650 expects to see. The practical effect is the same as this whole page's: nobody should pay for information that no use justifies.

3 · What do I procure, then?

In Portugal, the measured reality is that this conversation has not even happened yet: 0 mentions of LOD in 1,059 documents from architecture competitions (2010–2026) (meta-concurso [measured]). When the BIM requirement of DL 10/2024 (Decree-Law) arrives (2030), the vocabulary the tender documents will adopt is this one — it arrives in time for you to procure well before someone else procures on your behalf.

4 · Frequently asked questions

What is LOD, in plain words?

A scale from 100 to 500 that measures how much of an element's information is reliable: 100 is concept, 300 is defined and measurable, 500 is verified against the built work. Formal definition in the BIMForum LOD Specification.

Which LOD do I need for permitting or design?

LOD 200–300 for design basis and permitting; LOD 350 for discipline coordination. Above that, only with a concrete use that demands it — fabrication (400) or verified asset management (500).

Is LOD the same thing as level of detail?

No — detail is how much you see, development is how much you know. You procure the second.

What is LOIN and what does it have to do with LOD?

It is the European version (EN 17412-1, used by ISO 19650): information needs per element and per purpose, instead of a single scale. “LOD 300” is the conversational shortcut; LOIN is the language of the standard.

How much does it cost to move up a step?

In scan-to-BIM, typical Portuguese LOD 200–350 modelling comes in between €0.5 and €4.5 per m² from an existing point cloud; each step above the use that is needed multiplies the time without buying anything. The pricing guide has the full ranges.

5 · The next step

Want the price of a model with the right LOD?

The scan-to-BIM pricing guide has the ranges per m², by area and by complexity — survey and modelling, with LOD 200–350 declared and the accuracy stated separately.

Open the pricing guide